Please be advised that we will be performing a scheduled electrical maintenance at the Vancouver Data Center Facility during the following window:

Thursday February 25th, 2011 at 21:30PM PT to Friday February 26th, 2011 at 06:00AM PT

This maintenance is required to replace UPS batteries that have reached their end of life on UPS-6 and UPS-7.

This maintenance is NON SERVICE IMPACTING. The UPS will remain online for the duration of the maintenance, however there may be a portion of the maintenance that may require the UPS to be placed into bypass mode. Canadian Web Hosting and the appropriate electrical/mechanical staff will be present for the entire duration of this maintenance window.