Dear Customer,

Please be advised that we will be performing a scheduled AC maintenance at our Vancouver Harbour Cenre and Spencer Facility during the following window:

From Monday, September 12, 2011 to Friday, September 16, 2011 07:00-20:00 PT Daily (Sept 12-17, 14:00-03:00 GMT Daily)

This maintenance is necessary to perform needed repairs identified in our CRAC unit preventative maintenance.

We will be taking steps to reduce temperature fluctuations during this maintenance. Auxiliary air conditioning unit will be on site, however you may notice a slight increase in ambient temperature for a portion of
the maintenance. Canadian Web Hosting and the appropriate building/mechanical staff will be present for the duration of this maintenance window.